Hi.
im looking for way to create a day to day report for my project.
MS project 2010.
say my table looks like:
Start Finish Resource
Task 1 01.11 05.11 A
Task 2 03.11 06.11 B and A
Task 3 02.11 08.11 B
Task 4 05.11 06.11 C
What im looking for is a report like:
01.11
A:
Task 1
02.11
A:
B:
Task 3
03.11
A:
Task 1
Task 2
B:
Task 3
Task 2
04.11
A:
Task 1
Task 2
B:
Task 3
Task 2
05.11
A:
Task 1
B:
Task 3
C:
Task 4
06.11
A:
Task 2
B:
Task 3
Task 2
C:
Task 4
07.11
B:
Task 3
08.11
B:
Task 3
Is this possible? or do I have to use VBA?
All help is appreciated! Thank you!
Br.
Bjoern
im looking for way to create a day to day report for my project.
MS project 2010.
say my table looks like:
Start Finish Resource
Task 1 01.11 05.11 A
Task 2 03.11 06.11 B and A
Task 3 02.11 08.11 B
Task 4 05.11 06.11 C
What im looking for is a report like:
01.11
A:
Task 1
02.11
A:
B:
Task 3
03.11
A:
Task 1
Task 2
B:
Task 3
Task 2
04.11
A:
Task 1
Task 2
B:
Task 3
Task 2
05.11
A:
Task 1
B:
Task 3
C:
Task 4
06.11
A:
Task 2
B:
Task 3
Task 2
C:
Task 4
07.11
B:
Task 3
08.11
B:
Task 3
Is this possible? or do I have to use VBA?
All help is appreciated! Thank you!