G
greg
Hello,
I have a strange question.
I am importing data into a ms project workplan. Using a custom map.
It seems like if I import Work less than 8 hrs it will become 8 hrs.
So if task1 has work = 1 it will get imported as work = 8
In the options I have work is entered in hours.
is there some setting for this? or a way to import the correct data,
without MS Project rounding up?
thanks for any help
I have a strange question.
I am importing data into a ms project workplan. Using a custom map.
It seems like if I import Work less than 8 hrs it will become 8 hrs.
So if task1 has work = 1 it will get imported as work = 8
In the options I have work is entered in hours.
is there some setting for this? or a way to import the correct data,
without MS Project rounding up?
thanks for any help