L
LTN
Hi,
We are a mid-size software development company and are looking at
implementing an Enterprise Scheduling, Resource Planning and Timesheet
application in one.I have been looking into MS Project Server 2003. We
currently are using MS Project 2000 as a desktop app. I was wondering how
Microsoft has changed the timesheet functionality? Is there now built in
functionality that will prevent Project from automatically changing
previously entered actual time?
I was also reading on the site and one suggestion was to apply an add onto
MS Project for Timesheets for payroll. What capabilities does MS Project not
hold? Is there an 'all in one' solution?
I was also wondering if the resource leveling has been improved in Server
2003?
Thanks for your help in advance.
L
We are a mid-size software development company and are looking at
implementing an Enterprise Scheduling, Resource Planning and Timesheet
application in one.I have been looking into MS Project Server 2003. We
currently are using MS Project 2000 as a desktop app. I was wondering how
Microsoft has changed the timesheet functionality? Is there now built in
functionality that will prevent Project from automatically changing
previously entered actual time?
I was also reading on the site and one suggestion was to apply an add onto
MS Project for Timesheets for payroll. What capabilities does MS Project not
hold? Is there an 'all in one' solution?
I was also wondering if the resource leveling has been improved in Server
2003?
Thanks for your help in advance.
L