MS Project Server 2007 Calendar Creation

T

tina siryon

I have created three calendars in MS Project Server. The one I am having an issue with is
"365 Days Working" What I am trying to do is make everyday a working day. I edit the calendar and go to "work week", clicked on "details and selected "Sunday". I was able to put the "From as 12:00 AM and the "TO" as 12:00 AM, I was able to save Sunday but cannot save any other days The other days Monday through Saturday defaults to "From" 12:00 AM, and "To" as 1:00 AM. I also did hit the F2 key for editing the cell but did this not help.

Thanking you in advance for your assistance and having a forum for these types issues and discussions.

EggHeadCafe - Software Developer Portal of Choice
RSS / ATOM Feed Autodiscovery Class
http://www.eggheadcafe.com/tutorial...24-87830ce3779f/rss--atom-feed-autodisco.aspx
 
N

Nicole

Tina,
Try clicking in the first column of the row below the data that you are
entering. If you do not click out of that cell, it will not save your
updates and will default to 1 hour after your start time.

It took me a week to figure this one out. Very quirky.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top