MS Project Server Import Timesheets problem

C

chino

Hello,

I have started using project/project server in my company and I have a
problem with the import timesheet functionality found in "My tasks" page in
PWA. This is what happens:

I created a new project with MS project.
I added a bunch of tasks to my project and I assigned myself to them.
I published my project to project server.
I logged into PWA and navigated to "My Tasks". All the new tasks appeared
correctly.
I then navigated to "my timesheets" and input actual work for my tasks in
several days of the week.
Then I navigated back to "my tasks" and clicked on "Import Timesheets".
Here is the problem, because NO tasks appear to be imported for the
timesheet period selected. So I could not sync the timesheet with the tasks
progress.

After trying a bunch of different paths, I discovered that if I add a new
task directly from "My tasks", and input actual hours in the timesheet, that
task then shows up when clicking "import timesheet".

I have looked for any information on this but I was not successful. Does
anyone have a clue on how to make this work? It is very inconvenient to have
to sync these things by hand.

Thanks!
 
D

Dale Howard [MVP]

chino --

Did you actually SUBMIT the Timesheet for that time period? If not, do so,
and then try importing the actuals from the My Timesheet page to the My
Tasks page. Let us know if this helps.
 