I am fairly new to MS Project. When I set up the status report for my
resources it only sends the notification email to my resources the first time
I set up the report. I have set up the alert preferences to send out weekly
notifications and emails for overdue reports but emails are never sent. Even
if I manually request a status report it doesn't seem to send an email. The
only way I've gotten reminder emails to go out to the team is to delete the
existing status report and create a new one. Any suggestions?

Thanks,
Joe
 
D

Dale Howard [MVP]

Joe --

When you want to set e-mail reminders, "My resources" refers to resources
that meet one of the following criteria:

1. Resources below you in the RBS outline code structure
2. Resources that are team members in your projects

Do the people in question meet either of the above criteria? Let us know.
 
D

Dale Howard [MVP]

JoeJV --

Strange. Are you seeing errors in the application Event Log on the server
containing Project Server? Let us know.
 
J

JoeJV

OK. I'll have our sys admin check the log and let you know. It is very odd
considering that all other emails (e.g. project start, project end, etc.) are
sent just fine to my team :(