J
Jumenwoke
Hi all,
I have a 3 month's project and I need to use MS Project . But when I make
all the task entries, MS Project gives me a 9 month's timeline instead of the
required 3 months. Is this MS Project default timeline? I have to manually
change each task and input prescise hours and days for each task to override
MS Project unrealistic times applying the resources I have for each task.
Can someone explain the key things I need to do so that I can get MS Project
to use the required 3 months timeline instead of 9 months it is defaulting to.
I have a 3 month's project and I need to use MS Project . But when I make
all the task entries, MS Project gives me a 9 month's timeline instead of the
required 3 months. Is this MS Project default timeline? I have to manually
change each task and input prescise hours and days for each task to override
MS Project unrealistic times applying the resources I have for each task.
Can someone explain the key things I need to do so that I can get MS Project
to use the required 3 months timeline instead of 9 months it is defaulting to.