M
Matt M
Okay, got an interesting one here (I hope). My company wants to turn off the
automatic critical path identification function of MS project. However, when
we do that it appears to impact the use of dependencies. If the Calculation
Mode is set to Manual rather than Automatic, then the pushing of dependent
task dates does not occur. Is there a way to maintain the automatic
calculations, but turn off the critical path identification portion of it?
Thank you.
automatic critical path identification function of MS project. However, when
we do that it appears to impact the use of dependencies. If the Calculation
Mode is set to Manual rather than Automatic, then the pushing of dependent
task dates does not occur. Is there a way to maintain the automatic
calculations, but turn off the critical path identification portion of it?
Thank you.