Is it possible to change and/or update any project data
fields, other than Time Sheet data, using MS Project Web
Access? If I want to change an existing task's start date
for instance. If so how does one setup Project Server to
do this?
 
D

Dominic

Meinhard,

In the Customise Project Web Access section availabnle to Administrators you
can specify the update option of recording actual work per day or week - if
a resource enters actual work per day in the timescaled part of the screen
and they are the only resource assigned to the task the first day on which
they post actual work will be used to record the "Actual Start" for the task
when the updates are processed and used to update the project plan, if you
have more than one resource working on the same task the person who records
the earliest day on which they first worked on the task will determine the
"Actual Start" date the resource who enters the latest day where they worked
on the task will determine the "Actual Finish" date for the task.

--
Dominic Moss

www.projectability.co.uk

Helping people achieve more with Microsoft Project

Tel +44 8707 303 400
Fax +44 8707 303 500
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top