Daniel Leon
Help
When I view resources in MS Project web access, select a resource and
then select availability, I get tasking on non-working days such as
Sunday. The availability is zero on these days but I thought the
tasking should be reflective of the project in MS projest
professional. The project in MS project professional shows no tasking
on any nonworking days. I have set up an Enterprise standard calendar
and both the project and resource are using this calendar. This
problem is true with different rersources and different projects but
not all projects.
Also Any idea on how to match project professional "resource graph
view , and project web acess "resource availability . The red
overallocation of resources indicator on the graph view does not match
the same day when viewing resource availability on web acess.
Thanks in advance
When I view resources in MS Project web access, select a resource and
then select availability, I get tasking on non-working days such as
Sunday. The availability is zero on these days but I thought the
tasking should be reflective of the project in MS projest
professional. The project in MS project professional shows no tasking
on any nonworking days. I have set up an Enterprise standard calendar
and both the project and resource are using this calendar. This
problem is true with different rersources and different projects but
not all projects.
Also Any idea on how to match project professional "resource graph
view , and project web acess "resource availability . The red
overallocation of resources indicator on the graph view does not match
the same day when viewing resource availability on web acess.
Thanks in advance