Camille O
While trying to create a Master Project, I keep encountering a strange
problem. I insert a project and it automatically has a finsih date for
1/24/06 (which is the finish date of the master project assigned
automatically by MSProject) I have to expand the subtask in order for the
correct date to show up for that particular project, and this happens for
every new project I enter on my Master project. Then once I have done that
there are other times that the dates change back to the 1/24/06 date on every
project and I have to go back and expand each one for the correct dates to
show up again. Hope this makes sense and does anyone have a solution.
problem. I insert a project and it automatically has a finsih date for
1/24/06 (which is the finish date of the master project assigned
automatically by MSProject) I have to expand the subtask in order for the
correct date to show up for that particular project, and this happens for
every new project I enter on my Master project. Then once I have done that
there are other times that the dates change back to the 1/24/06 date on every
project and I have to go back and expand each one for the correct dates to
show up again. Hope this makes sense and does anyone have a solution.