MS Project

C

Camille O

While trying to create a Master Project, I keep encountering a strange
problem. I insert a project and it automatically has a finsih date for
1/24/06 (which is the finish date of the master project assigned
automatically by MSProject) I have to expand the subtask in order for the
correct date to show up for that particular project, and this happens for
every new project I enter on my Master project. Then once I have done that
there are other times that the dates change back to the 1/24/06 date on every
project and I have to go back and expand each one for the correct dates to
show up again. Hope this makes sense and does anyone have a solution.
 
J

Jan De Messemaeker

Hi Camille,

I suspect your Master Project has the option "Schedule from Finish Date"
which causes every task to be scheduled as late as possible. Change that to
"from Start date" in Project, Project Information
HTH
 
C

Camille O

Thanks Jan,

I did check, however it is showing 'Scheduled from Start Date", any other
suggestions?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top