MS-Project

R

Rod Gill

Hi,

Update the task with actual progress so far, then drag the incomplete part
into the future when you think it will be restarted. The actual part gets
left behind as Project automatically splits the task.

--
For VBA posts, please use the public.project.developer group.
For any version of Project use public.project
For any version of Project Server use public. project.server

Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.project-systems.co.nz/
Email rodg AT project-systems DOT co DOT nz
 