I have a MS Project 2000 and I have two questions (may be for beginners :)

- How to enter a recurrent task that happens regularly?

- On the Gantt chart , can we see the summary recurrent task as a line that
includes milestones showed inside it (meaning the repeated tasks showed as
milestones inside the line that represents the recurrent summary task) ?

Thanks in advance

Fayez
 
J

JulieS

Hi Fayez,

1) To create a recurring task choose Insert > Recurring task in the
menu.

2) I'm afraid not. The summary recurring task is not a long summary
task line like other summary tasks. You will see each occurance
appearing at the summary line.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 
A

a

Thanks a lot

JulieS said:
Hi Fayez,

1) To create a recurring task choose Insert > Recurring task in the menu.

2) I'm afraid not. The summary recurring task is not a long summary task
line like other summary tasks. You will see each occurance appearing at
the summary line.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top