Well, it can't be shown as a "path" since the calendar view is, well, a
calender. So, theoretically it can, but I'm unsure about how useful that
would be. To show tasks that are on the critical path, e.g. filter with
"Critical" equal to "Yes". Display only those on a calendar.

--rms

www.rmschneider.com
 
D

Dale Howard [MVP]

jurie --

Open the project and apply the Calendar view. Click Format - Bar Styles.
In the Bar Styles dialog, select the Critical item in the Task Type list and
then specify your formatting for Critical tasks, such as red bars. Click
the OK button when finished. Hope this helps.
 