MS PS2007: My baseline1 total summary does not add up correctly

P

PedroJose

Hi,

I use the baseline1 field to record the estimates that people provide for
their tasks. I save the info and have flags setup for variance. The problem
is that in some cases (not all projects have this problem), the summary level
total (level0) does not add up correctly. The case that i am looking at
right now should add up to 990, and instead it displays 989.13. All tasks
have the correct info and lower lebvel summary tasks add up correctly. When
I update the top level summary baseline! from subtasks and to all summary
tasks, the total is not correct. This happens only in some cases... any
ideas?? this is very annoying because we actually evaluate people based on
how well they do with estimates and evaluate completed projects based on this
info, and it is incorrect!!!
 