When updating your schedule, and a planned task is no longer needed,
is there any better option than these:
1. Delete the task - then all planning information is lost
2. Leave the task alone - then it continues to appear in filters of
uncompleted tasks
3. Mark the task completed - then the "effort" attributed to it is
wrong
4. Set work to 0 and mark completed - then the baseline view is
incorrect (shows baseline task as a milestone in the Gantt chart
display)
Rob Wood
is there any better option than these:
1. Delete the task - then all planning information is lost
2. Leave the task alone - then it continues to appear in filters of
uncompleted tasks
3. Mark the task completed - then the "effort" attributed to it is
wrong
4. Set work to 0 and mark completed - then the baseline view is
incorrect (shows baseline task as a milestone in the Gantt chart
display)