In project 2002, modifications were made to a live published project plan
where tasks without actuals had been removed and new tasks have been added.
The project was published and appears correctly within Project Center,
however the old tasks still appear in the resource timesheets and the new
tasks do not appear. The old tasks do not have a X next to them, and still
appear to be active on the timesheet.
Is there a reason why these removed tasks would still appear? Is there a
workaround to fix this?
Thank you
where tasks without actuals had been removed and new tasks have been added.
The project was published and appears correctly within Project Center,
however the old tasks still appear in the resource timesheets and the new
tasks do not appear. The old tasks do not have a X next to them, and still
appear to be active on the timesheet.
Is there a reason why these removed tasks would still appear? Is there a
workaround to fix this?