MSP 2007 resources help

G

Guest

Hi all,

Three questions:
1. What the constraint A<B,C means and how can I entering in the MSP?
2. I have 3 kinds of human resources. Lets say for example, kind A are
engineers. I have 8 of them and everyone is costing 1500 Euros/month. Task A
needs 4 engineers. How can I assign them to the task and add the appropriate
cost?
3. I have 3 machines as a resource. Each machine has a usage cost of 3000
euros per task and function cost 2400 euros per month. How can I assign them
in the appropriate tasks? And how can I distribute their cost?

Thank you in advance
 
J

José Miguel Piñeres

Hello!

Welcome to this Microsoft Project General Questions newgroup and thank you
for posting.

1. I think that you need to clarify your concept about task constraints. For
more information, please visit the following page:
http://office.microsoft.com/en-us/project/HA101130731033.aspx?pid=CH100666481033.

Seems to me that questions 2 & 3 are pretty similar. Resource assignment to
tasks is covered in MSP Help. Please visit the following page:
http://office.microsoft.com/en-us/project/HA101935931033.aspx

I hope this helps. Please let us know how you get along with it.

Best regards,

--
If this answer has been of help, please consider rating it.

José Miguel Piñeres
MCITP | MCT
San José, Costa Rica
http://projectpedia.blogspot.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top