W
WDP
After reading all the material available for MS project 2007 I have still 2
questions:
* If a team member is sick, how somebody can introduce his/her ours using
PWA? Who can introduce their hours?
* I have noticed that when using the PWA and updating actual work and
remaining work, in the Project center, task work views, I cannot see
the updated results even they have been approve by the PWA project manager.
I only see them when I connect to MS project 2007 to the
server, and then I got them updated. Is there a reason for that? Is there
any way to get updated results?
Regards,
WDP
questions:
* If a team member is sick, how somebody can introduce his/her ours using
PWA? Who can introduce their hours?
* I have noticed that when using the PWA and updating actual work and
remaining work, in the Project center, task work views, I cannot see
the updated results even they have been approve by the PWA project manager.
I only see them when I connect to MS project 2007 to the
server, and then I got them updated. Is there a reason for that? Is there
any way to get updated results?
Regards,
WDP