B
Brian
Can somebody shed some light on how to update a project plan with actual work
that has been submitted by resources via PWA in MSP 2007? I am specified as
my own Timesheet Manager and Assignment Owner on the Edit Resource page.
When I enter actual work in the timesheet view and submit, I get a message
that the system automatically approved it and I don't see anything similar to
the Updates tab in the 2003 version. Can somebody point me down the right
road?
Thanks,
Brian
that has been submitted by resources via PWA in MSP 2007? I am specified as
my own Timesheet Manager and Assignment Owner on the Edit Resource page.
When I enter actual work in the timesheet view and submit, I get a message
that the system automatically approved it and I don't see anything similar to
the Updates tab in the 2003 version. Can somebody point me down the right
road?
Thanks,
Brian