K
Kathy S
MSP Professional 2003 SP3 & PWA 2003 - Need help understanding why the
assignment's finish dates in MSP's
assignments view (Window > Split Window > Resource Schedule) retains
the tasks' original finish dates even when the task duration increases
and pushes out the tasks finish dates. The tasks are in the future,
no actual work hours, fixed duration, not effort driven, no
predecessors, resources could be enterprise or local or both. It does
not happen to every task. Calculation mode is set to automatic.
Thanks,
Kathy