Emma Gedge
Hi
As described in a previous help request I have multiple resources wh
all work different hours each day, different days each week - there i
absolutely no pattern to their shifts. They will either be on a day,
24 hour, a rest day, annual leave or out of area/on a course.
I have tried to get around this problem by adding each week and the
customising it through work week to their actual shifts.
I have successfully added 9 weeks so far but when adding a tent
different work week MSP is consistently crashing every time I try.
Is 9 the limit of work weeks I can add?
Is there any way of making this work?
Thanks
Emm
As described in a previous help request I have multiple resources wh
all work different hours each day, different days each week - there i
absolutely no pattern to their shifts. They will either be on a day,
24 hour, a rest day, annual leave or out of area/on a course.
I have tried to get around this problem by adding each week and the
customising it through work week to their actual shifts.
I have successfully added 9 weeks so far but when adding a tent
different work week MSP is consistently crashing every time I try.
Is 9 the limit of work weeks I can add?
Is there any way of making this work?
Thanks
Emm