K
Kurt Petteloot
Hi,
Some of the resources work on several projects at the same time. What is
usually done is that an agreement is made between the PM's about the
availability of these shared resources for their projects. For instance
project mgr A and B agree that resource 'x' will work on project A for
2days/week and 3days/week on project B until a specific date, after which the
agreement could change (for instance 1d/wk on project A and 4d/wk on project
B).
Project manager A has to level this resource using a maximum availability of
40% until the day when his availability drops to 20%. Similar constraints for
project manager B.
Te challenge is to allow these project managers to use the automatic
leveling functionality which is based on the availability set for the
enterprise resource. However this availability is maintained centrally. This
means that there is no way to capture the availability of that resource for a
specific project.
Does anyone know of any best practices or possible solutions? How do
organizations manage the fact that they use resources that are shared across
concurrently executing projects?
Thanks for any feedback
Kind Regards
Kurt
Some of the resources work on several projects at the same time. What is
usually done is that an agreement is made between the PM's about the
availability of these shared resources for their projects. For instance
project mgr A and B agree that resource 'x' will work on project A for
2days/week and 3days/week on project B until a specific date, after which the
agreement could change (for instance 1d/wk on project A and 4d/wk on project
B).
Project manager A has to level this resource using a maximum availability of
40% until the day when his availability drops to 20%. Similar constraints for
project manager B.
Te challenge is to allow these project managers to use the automatic
leveling functionality which is based on the availability set for the
enterprise resource. However this availability is maintained centrally. This
means that there is no way to capture the availability of that resource for a
specific project.
Does anyone know of any best practices or possible solutions? How do
organizations manage the fact that they use resources that are shared across
concurrently executing projects?
Thanks for any feedback
Kind Regards
Kurt