I am an intermediate MSP user, new to MSP Server. A
couple of issues I have noted using server I would like
to fix if possible;
1. When the server sends out task update requests to the
resources, I notice that the email the resources receive,
only gives the "Task Description" and does not include
the "Task ID Number". In a large project this will make
it difficult for the resource to review the overall
project for impact to predecessors/sucessors without
paging down and reading each activity. Is there a way to
turn on the Task ID Number for these messages?
2. When a resource updates a task, it appears that he/she
can do so without consideration for the schedule logic,
for example the resource can status a task complete
before its predecessor has been started/or completed. Is
this correct? Does this imply that the PMgr must carfully
review each updated task to ensure the logic has not been
compromised? Presumably then rejecting incorrect task
status updates?
Thank you.
couple of issues I have noted using server I would like
to fix if possible;
1. When the server sends out task update requests to the
resources, I notice that the email the resources receive,
only gives the "Task Description" and does not include
the "Task ID Number". In a large project this will make
it difficult for the resource to review the overall
project for impact to predecessors/sucessors without
paging down and reading each activity. Is there a way to
turn on the Task ID Number for these messages?
2. When a resource updates a task, it appears that he/she
can do so without consideration for the schedule logic,
for example the resource can status a task complete
before its predecessor has been started/or completed. Is
this correct? Does this imply that the PMgr must carfully
review each updated task to ensure the logic has not been
compromised? Presumably then rejecting incorrect task
status updates?
Thank you.