MSP Summary task

A

AR S S Iyer

Why summart task is showing fraction, even though calender and
duration are set correct?this has occured after i have rescheduled the
entire project, i have inserted some new task % complete 0%
 
J

Jan De Messemaeker

Hi,

What is "correct"? Go to Tools, Options, View, and set the upmost date
format from the lookup list (the one with time of day). That will show you
that the finish hour of the summary task is not the same as the start hour
of the summary task. There probably is a mismatch between teh definition of
"hours per day" in teh Calendar options with the working time in the Project
Calendar.

Hope this helps,
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top