Stu@Grey
Hi, we recently switched to a master project arrangement for all our
projects, which brought on the need to use resource usage view to hand edit
the distribution of remaining work for each resource/task.
This has generally worked fine, except recently we've found this very
annoying problem - when we alter the work values, MSP is actually also
modifying the actual work values with the same numbers - why would it be
doing this?
Heres an example:
Task1: Res1 has completed 5 hours of actual work, and has 4 hours remaining.
These are scheduled for a Monday in 3 weeks, and we want to shift those 4
hours to the Wednesday of that week. Previously we could just edit those
hours in resource usage view via the work cells in the time-phased table, but
sometimes we see this:the 4 hours are allocated as actual work (thus work
also equals 4 hours for that column), as though the resource had now
completed those 4 hours.
FWIW, the status date is correctly set to where the actual work finishes,
and all remaining work and the cells we're trying to modify are well past the
status date, so I cannot understand why its doing this.
Any tips?
Stu.
projects, which brought on the need to use resource usage view to hand edit
the distribution of remaining work for each resource/task.
This has generally worked fine, except recently we've found this very
annoying problem - when we alter the work values, MSP is actually also
modifying the actual work values with the same numbers - why would it be
doing this?
Heres an example:
Task1: Res1 has completed 5 hours of actual work, and has 4 hours remaining.
These are scheduled for a Monday in 3 weeks, and we want to shift those 4
hours to the Wednesday of that week. Previously we could just edit those
hours in resource usage view via the work cells in the time-phased table, but
sometimes we see this:the 4 hours are allocated as actual work (thus work
also equals 4 hours for that column), as though the resource had now
completed those 4 hours.
FWIW, the status date is correctly set to where the actual work finishes,
and all remaining work and the cells we're trying to modify are well past the
status date, so I cannot understand why its doing this.
Any tips?
Stu.