T
TomG
Hi,
I am working on MS Project timephased data via an Access database.
Everything works fine with data for
1 Assignment remaining work
2 Assignment actual work
3 Assignment actual overtime work
4 Assignment baseline work
5 Assignment baseline cost
BUT - I want to use "Assignment actual cost" (CONV_VALUE = 6) and the data
is just not coming across into the MSP_TIMEPHASED_DATA table.
I know the calculated Actual Cost information is present in Project 2003
because I can see it in the Resource Usage view. I know the Actual Cost
information is NOT
present in MSP_TIMEPHASED_DATA because there is no row in the table with
TD_FIELD_ID = 6.
Here's the weird thing: When I enter the Actual Cost information manually
into Project 2003, it comes across into the MSP_TIMEPHASED_DATA fine. It's
the automatically created data which will not transfer.
For example: If the calculated Actual Cost = £400.00, it does not get
written to MSP_TIMEPHASED_DATA. If I change the value to £401.00, it gets
written to the table!
Is this a known problem?
I'd be very grateful for any help.
Regards,
Tom
I am working on MS Project timephased data via an Access database.
Everything works fine with data for
1 Assignment remaining work
2 Assignment actual work
3 Assignment actual overtime work
4 Assignment baseline work
5 Assignment baseline cost
BUT - I want to use "Assignment actual cost" (CONV_VALUE = 6) and the data
is just not coming across into the MSP_TIMEPHASED_DATA table.
I know the calculated Actual Cost information is present in Project 2003
because I can see it in the Resource Usage view. I know the Actual Cost
information is NOT
present in MSP_TIMEPHASED_DATA because there is no row in the table with
TD_FIELD_ID = 6.
Here's the weird thing: When I enter the Actual Cost information manually
into Project 2003, it comes across into the MSP_TIMEPHASED_DATA fine. It's
the automatically created data which will not transfer.
For example: If the calculated Actual Cost = £400.00, it does not get
written to MSP_TIMEPHASED_DATA. If I change the value to £401.00, it gets
written to the table!
Is this a known problem?
I'd be very grateful for any help.
Regards,
Tom