C
c.tambone
Hello,
I have installed Project Server 2007 and Project Professional 2007 and
I need to retrieve timephased data directly using queries on the DB.
In Project 2003 I used the "expand timephased data" option in the File
Options Save dialog box in order to populate that table and then I
queried on the MSP_TIMEPHASED_DATA table.
In Project 2007 I find the table but it is always empty, how can I set
the same option that I do not find anymore in the File Options Save
dialog box, in order to retrieve the planned cost and actual cost,
planned work actual work TimePhased?
Is there any suggestion on how to do it?
Thanks in advance
Claudia
I have installed Project Server 2007 and Project Professional 2007 and
I need to retrieve timephased data directly using queries on the DB.
In Project 2003 I used the "expand timephased data" option in the File
Options Save dialog box in order to populate that table and then I
queried on the MSP_TIMEPHASED_DATA table.
In Project 2007 I find the table but it is always empty, how can I set
the same option that I do not find anymore in the File Options Save
dialog box, in order to retrieve the planned cost and actual cost,
planned work actual work TimePhased?
Is there any suggestion on how to do it?
Thanks in advance
Claudia