R
Rhardwick
Does anyone know how I can repopulate/reset the data in MSP_WEB_WORK?
Some how our web work table has become out of line with Time phased
actual work protected. This means that a large number of hours have
disappeared from PWA time sheets and approved tasks seem to go into a
black hole. This is causing a big problem for us as all our reporting
is done through PWA.
I have now written some SQL view which report on Time phased actual
work protected but I cant get the report to line up with previous
reports generated through PWA.
I have all the relevant service packs installed
Any ideas?
Some how our web work table has become out of line with Time phased
actual work protected. This means that a large number of hours have
disappeared from PWA time sheets and approved tasks seem to go into a
black hole. This is causing a big problem for us as all our reporting
is done through PWA.
I have now written some SQL view which report on Time phased actual
work protected but I cant get the report to line up with previous
reports generated through PWA.
I have all the relevant service packs installed
Any ideas?