S
ST
Hi,
When I use the MS Project Pro 2007 (SP1) "Project" Import wizard, I set
certain resources as "keep local with base calendar', yet MS Project Server
creates them as resources Server! After the import I see these 'local'
resources created on Server. They appear in the Resource Center, and can be
seen in 'Resources and Users' option within PWA's Server Settings > 'Delete
Enterprise Objects'. But, are are NOT visible in PWA's Server Settings >
Manage Users (Security Settings section).
In the Resource Sheet of the imported file the resource has been converted
to an enterprise resource (not local as was selected).
Is this a bug?
/Spiro Theopoulos.
When I use the MS Project Pro 2007 (SP1) "Project" Import wizard, I set
certain resources as "keep local with base calendar', yet MS Project Server
creates them as resources Server! After the import I see these 'local'
resources created on Server. They appear in the Resource Center, and can be
seen in 'Resources and Users' option within PWA's Server Settings > 'Delete
Enterprise Objects'. But, are are NOT visible in PWA's Server Settings >
Manage Users (Security Settings section).
In the Resource Sheet of the imported file the resource has been converted
to an enterprise resource (not local as was selected).
Is this a bug?
/Spiro Theopoulos.