I'm trying the 2010 beta, and very nice it is too - I LOVE the team planner
view.
However, I'm having trouble with it not seeming to honour dependencies
between roll-ups.
I have some work that I want to happen in two phases, and so have a roll-up
with the tasks in the first phase, linked to the roll-up with tasks in the
second pahase by a FS dependency.
In MSP 2007, when levelling, it would nicely put everything in the second
phase after the first one (using ID only levlling).
But in 2010 it's scheduled the work in the second phase before the end oif
the first one. Those tasks are pretty fragmented too.
It looks like it's trying to assign that resource to spare time in the first
phase.
Any clues?
view.
However, I'm having trouble with it not seeming to honour dependencies
between roll-ups.
I have some work that I want to happen in two phases, and so have a roll-up
with the tasks in the first phase, linked to the roll-up with tasks in the
second pahase by a FS dependency.
In MSP 2007, when levelling, it would nicely put everything in the second
phase after the first one (using ID only levlling).
But in 2010 it's scheduled the work in the second phase before the end oif
the first one. Those tasks are pretty fragmented too.
It looks like it's trying to assign that resource to spare time in the first
phase.
Any clues?