J
Johanna from Canada
Hi there,
Curious to know if anyone out there is using 2002 for non-project time
tracking?
The problem is that my organization does not want to impose duplicate
effort (entering time in PWA and another time tracking tool). I
believe it's not ideal; however, it's either the employee enters their
time in the time tracking tool, which the PMs do not have access to,
and report time to the PMs directly, or they can enter it themselves in
PWA.
A project to look at the whole problem was cancelled. Essentially,
upper management doesn't want to spend any money and are relying on my
limited MSPS knowledge to solve the problem.
I believe the problem is complication due to reporting requirements and
the hierarchy of the non-project time categories.
The existing non-project time categories are:
Categories -> Sub-Categories -> Activities -> Sub-activities (not all
activities have sub-activities)
Examples:
Service and Delivery -> Application Maintenance -> Application XYZ ->
Application Module XYZ
I need to be able to report to the sub-activity level. I could create
a project for every Sub-activity, and perhaps create enterprise fields
to classify the projects; however, there will be hundreds of projects
and I don't see how you could establish a hierarchy that would display
to the PWA users. Also, although, only applicable staff would be
assigned to the project, this would not be user friendly and a
maintenance nightmare.
I'm hoping someone, an MSPS guru, will put me out of my misery and tell
me it cannot be done...in MSPS 2002 atleast. then again, if I am
missing a simple solution, it would be appreciated too.
Whatever you do, no need to point out the obvious...MSPS is a project
management tool.
Thanks!
Johanna
BTW: Gary Chefetz -- if you are out there, I have purchased two of your
books (Implementing Enterprise Portfolio Management with MSPS 2002 and
Administering an Enterprise PMO using MSPS 2003) and loved them both!
Curious to know if anyone out there is using 2002 for non-project time
tracking?
The problem is that my organization does not want to impose duplicate
effort (entering time in PWA and another time tracking tool). I
believe it's not ideal; however, it's either the employee enters their
time in the time tracking tool, which the PMs do not have access to,
and report time to the PMs directly, or they can enter it themselves in
PWA.
A project to look at the whole problem was cancelled. Essentially,
upper management doesn't want to spend any money and are relying on my
limited MSPS knowledge to solve the problem.
I believe the problem is complication due to reporting requirements and
the hierarchy of the non-project time categories.
The existing non-project time categories are:
Categories -> Sub-Categories -> Activities -> Sub-activities (not all
activities have sub-activities)
Examples:
Service and Delivery -> Application Maintenance -> Application XYZ ->
Application Module XYZ
I need to be able to report to the sub-activity level. I could create
a project for every Sub-activity, and perhaps create enterprise fields
to classify the projects; however, there will be hundreds of projects
and I don't see how you could establish a hierarchy that would display
to the PWA users. Also, although, only applicable staff would be
assigned to the project, this would not be user friendly and a
maintenance nightmare.
I'm hoping someone, an MSPS guru, will put me out of my misery and tell
me it cannot be done...in MSPS 2002 atleast. then again, if I am
missing a simple solution, it would be appreciated too.
Whatever you do, no need to point out the obvious...MSPS is a project
management tool.
Thanks!
Johanna
BTW: Gary Chefetz -- if you are out there, I have purchased two of your
books (Implementing Enterprise Portfolio Management with MSPS 2002 and
Administering an Enterprise PMO using MSPS 2003) and loved them both!