P
projectserverdragon
I have enterprise and local resource sharing tasks.
I process updates to get the actuals updated, however I have to maunually
update compltion due to having local resources.
this puts me out of sync so I sync and wind up w/ a greater# of hours than
what is true because this complex engine auto inserts actual work for the
local resource.
Is there a sane means of managing tasks w/ both types of resources?
I process updates to get the actuals updated, however I have to maunually
update compltion due to having local resources.
this puts me out of sync so I sync and wind up w/ a greater# of hours than
what is true because this complex engine auto inserts actual work for the
local resource.
Is there a sane means of managing tasks w/ both types of resources?