PSD:
You don't really have an historical record by transaction visible in My
Tasks before you archive a project, let alone after. If you are using
Timesheets, the ones not associated with My Tasks, then you do have a
transaction history to go back to. If you use My Tasks exclusively, then you
don't have access to the transactional data, although I believe the system
retains these in an internally used table that requires decoding. As an
undocumented transactional table, it's useless to end users unless you can
reverse engineer it.
--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting:
http://www.msprojectexperts.com
Project Server Training:
http://www.projectservertraining.com
Project Server FAQS:
http://www.projectserverexperts.com
Project Server Help Blog:
http://www.projectserverhelp.com