I have completed the processes to archive projects:
1. Update all resource to proposed & publish
2. Add project to Category built for Completed Projects (Deny Open and Save).
Step 1 flushes the assignments from timesheets.
Step 2 makes the project unavailable from MS Project
However...
I currently allow resource to "Assign themselves to existing tasks" if they
are on the project team. I have found that these resources can still add
tasks from my "Archived" projects using this function.
Is there a way to remove these projects from the Project Center views and
also remove them from the list of available projects within "Assign myself to
existing tasks"?
Thanks in advance my friends!
1. Update all resource to proposed & publish
2. Add project to Category built for Completed Projects (Deny Open and Save).
Step 1 flushes the assignments from timesheets.
Step 2 makes the project unavailable from MS Project
However...
I currently allow resource to "Assign themselves to existing tasks" if they
are on the project team. I have found that these resources can still add
tasks from my "Archived" projects using this function.
Is there a way to remove these projects from the Project Center views and
also remove them from the list of available projects within "Assign myself to
existing tasks"?