MSPS 2003 Project Archiving ?

  • Thread starter projectserverdragon
  • Start date
P

projectserverdragon

I have completed the processes to archive projects:

1. Update all resource to proposed & publish
2. Add project to Category built for Completed Projects (Deny Open and Save).

Step 1 flushes the assignments from timesheets.
Step 2 makes the project unavailable from MS Project

However...

I currently allow resource to "Assign themselves to existing tasks" if they
are on the project team. I have found that these resources can still add
tasks from my "Archived" projects using this function.

Is there a way to remove these projects from the Project Center views and
also remove them from the list of available projects within "Assign myself to
existing tasks"?

Thanks in advance my friends!
 
P

projectserverdragon

Cool, I got the filter for Project Center.

Might there be anything I can do to remove the projects from "Assign myself
to existing tasks"?
 
S

Sean Hanson

Apologize, meant to put that in the first post, no these will still be
available for self assignment, sorry.
--
Sean Hanson

http://www.randsmanagement.com
Mass Resource Tool for 2007
Project Server 2007 Archive Tool
SRS Reports
 
P

projectserverdragon

Just another reason to get to 2007 platform.

You're alright Sean, have a good one!
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top