I was wondering if someone can help me. I am in the process of setting up MS
Project Server 2007 with a view to interfacing with our existing timesheet
system. One of the pieces of information we currently track is whether a
task is billable or non-billable. However, I can't see how to flag this -
either on the task in MS Project or when entering actuals in the timesheet?
I can set up new timesheet classifications but can't see how to flag these as
billable or not? I have even tried setting the resource rates as zero, but
all the hours are still showing in ActualWorkBillable in the
MSP_TimesheetActual table in the ProjectServer_Reporting database in SQL
Server 2005.
Project Server 2007 with a view to interfacing with our existing timesheet
system. One of the pieces of information we currently track is whether a
task is billable or non-billable. However, I can't see how to flag this -
either on the task in MS Project or when entering actuals in the timesheet?
I can set up new timesheet classifications but can't see how to flag these as
billable or not? I have even tried setting the resource rates as zero, but
all the hours are still showing in ActualWorkBillable in the
MSP_TimesheetActual table in the ProjectServer_Reporting database in SQL
Server 2005.