T
Tim Mccoy
Is there an easy way to get non-working time from MS Project 2003 (setup for
non-server environment) to MS Project Server 2007 (setup for server
environment)?
We are converting project schedules from 2003 to 2007 and need to get the
non-working time converted to 2003. The resources are already in the 2007
enterprise resource pool, just not the non-working time. We can do it
manually, but trying to avoid spending the time if we don’t need to.
Thank you in advance!
Tim
non-server environment) to MS Project Server 2007 (setup for server
environment)?
We are converting project schedules from 2003 to 2007 and need to get the
non-working time converted to 2003. The resources are already in the 2007
enterprise resource pool, just not the non-working time. We can do it
manually, but trying to avoid spending the time if we don’t need to.
Thank you in advance!
Tim