T
Tim Mccoy
I created a plan on the server that has all our resources in it and
no tasks. In the plan I have a custom Resource Usage view I created
with some Group By's to help see resource availability.
I created the plan and view in Feb of 2008 and the view always opens
to Feb 2008. I've tried saving the plan while viewing the Nov 2008
information, changing the dates in the Project Information (both in
the plan and the Enterprise Resource Pool) to November dates, adding
a start milestone in the plan Gantt, using the adjust dates button on
the analyze toolbar, and nothing seems to work.
Can somebody advise on a solution? I don't want to re-create the
plan every month just so it can open to the current date.
Thank you!
no tasks. In the plan I have a custom Resource Usage view I created
with some Group By's to help see resource availability.
I created the plan and view in Feb of 2008 and the view always opens
to Feb 2008. I've tried saving the plan while viewing the Nov 2008
information, changing the dates in the Project Information (both in
the plan and the Enterprise Resource Pool) to November dates, adding
a start milestone in the plan Gantt, using the adjust dates button on
the analyze toolbar, and nothing seems to work.
Can somebody advise on a solution? I don't want to re-create the
plan every month just so it can open to the current date.
Thank you!