MSPS 2007 - Question Regarding Using Multiple Issues Lists

T

Tim Mccoy

How can I work around MSPS 2007 not allowing me to have multiple issues lists?

I’ve got my out of the box “Issues†list on the project workspace. I’ve
added another issues list, which I called “Action Itemsâ€. I get an error
24018, 24016, and 2600. The message indicates I can only have one list of
this type.

I like the “Issues†template because it allows me to link to other items in
the workspace such as documents.

Is there a work around?

Thank you!

Tim

Here is the full error:

Your ReportingWSSSync job failed. Its current state is FailedNotBlocking.
It was 0% complete. It entered the queue at 01/22/2010 11:26:44.

To get more information about the job failure, please go to Project Web
Access. Select Personal Settings from the left menu. Then select My Queued
Jobs.

The errors returned from the queue are as follows:
Error ID: 24018
Error ID: 24016
Error ID: 26000

Detailed error below - send it to the administrator for more detailed
troubleshooting.

<?xml version="1.0" encoding="utf-16"?>
<errinfo>
<general>
<class name="Reporting Wss list sync failed">
<error id="24018" name="ReportingWssSyncListFailed"
uid="f14e4bb7-7142-4613-8171-0e7790033f36" SPListType="1100" Error="Project
with UID 'a69d2c3c-577e-4497-aa64-f8c10451c6f9' has more then one SPLists
with template type 1100. WSS transfer can be done only for projects with only
one list of this type" />
<error id="24018" name="ReportingWssSyncListFailed"
uid="75f48326-5a87-4953-9434-fe3bd34f0bd0" SPListType="1100" Error="Project
with UID 'a69d2c3c-577e-4497-aa64-f8c10451c6f9' has more then one SPLists
with template type 1100. WSS transfer can be done only for projects with only
one list of this type" />
<error id="24018" name="ReportingWssSyncListFailed"
uid="87912cbc-a6e0-43c8-9721-1f27ac2ad631" SPListType="1100" Error="Project
with UID 'a69d2c3c-577e-4497-aa64-f8c10451c6f9' has more then one SPLists
with template type 1100. WSS transfer can be done only for projects with only
one list of this type" />
<error id="24018" name="ReportingWssSyncListFailed"
uid="9daac145-5cb3-4e33-9649-fda0cfc95ab1" SPListType="1100" Error="Project
with UID 'a69d2c3c-577e-4497-aa64-f8c10451c6f9' has more then one SPLists
with template type 1100. WSS transfer can be done only for projects with only
one list of this type" />
<error id="24018" name="ReportingWssSyncListFailed"
uid="810d8356-2af2-4d34-837e-e8c1bb36f298" SPListType="1100" Error="Project
with UID 'a69d2c3c-577e-4497-aa64-f8c10451c6f9' has more then one SPLists
with template type 1100. WSS transfer can be done only for projects with only
one list of this type" />
<error id="24018" name="ReportingWssSyncListFailed"
uid="63591fd3-47ba-41f8-9813-747c3c4e21d4" SPListType="1100" Error="Project
with UID 'a69d2c3c-577e-4497-aa64-f8c10451c6f9' has more then one SPLists
with template type 1100. WSS transfer can be done only for projects with only
one list of this type" />
</class>
<class name="Reporting message processor failed">
<error id="24016" name="ReportingWSSSyncMessageFailed"
uid="bcbd768d-ea3d-411a-9a2c-f4d61fb0ea07"
QueueMessageBody="ProjectUID='a69d2c3c-577e-4497-aa64-f8c10451c6f9'.
ForceFullSync='False'" Error="RDS failed while trying to sync one or more SP
lists. The RDS queue message will be retried." />
<error id="24016" name="ReportingWSSSyncMessageFailed"
uid="0255363b-fc41-435d-966c-5d229225a388"
QueueMessageBody="ProjectUID='a69d2c3c-577e-4497-aa64-f8c10451c6f9'.
ForceFullSync='False'" Error="RDS failed while trying to sync one or more SP
lists. The RDS queue message will be retried." />
<error id="24016" name="ReportingWSSSyncMessageFailed"
uid="7b19ae18-4daa-4029-ac19-4dbf50b8f850"
QueueMessageBody="ProjectUID='a69d2c3c-577e-4497-aa64-f8c10451c6f9'.
ForceFullSync='False'" Error="RDS failed while trying to sync one or more SP
lists. The RDS queue message will be retried." />
<error id="24016" name="ReportingWSSSyncMessageFailed"
uid="f28427ab-e218-472c-a66e-b5ad6fee9db0"
QueueMessageBody="ProjectUID='a69d2c3c-577e-4497-aa64-f8c10451c6f9'.
ForceFullSync='False'" Error="RDS failed while trying to sync one or more SP
lists. The RDS queue message will be retried." />
<error id="24016" name="ReportingWSSSyncMessageFailed"
uid="7400cb34-7aaa-4adb-a1cd-b0b4576e296b"
QueueMessageBody="ProjectUID='a69d2c3c-577e-4497-aa64-f8c10451c6f9'.
ForceFullSync='False'" Error="RDS failed while trying to sync one or more SP
lists. The RDS queue message will be retried." />
<error id="24016" name="ReportingWSSSyncMessageFailed"
uid="03ce40c5-06ad-4dc2-a507-d7a8ea6b26d2"
QueueMessageBody="ProjectUID='a69d2c3c-577e-4497-aa64-f8c10451c6f9'.
ForceFullSync='False'" Error="RDS failed while trying to sync one or more SP
lists. The RDS queue message will be retried." />
</class>
<class name="Queue">
<error id="26000" name="GeneralQueueJobFailed"
uid="4e9256cf-2737-489c-bd58-bafbfd7b3cfe"
JobUID="768abb3f-5748-4391-8343-5d78a0157a98" ComputerName="AQSNTOSP02"
GroupType="ReportingWSSSync" MessageType="WSSSyncMessageEx" MessageId="1"
Stage="" />
</class>
</general>
</errinfo>

You can do the following:
1. Try troubleshooting using the error IDs, error XML.
2. Contact administrator with your jobID
(768abb3f-5748-4391-8343-5d78a0157a98) and error XML.

To turn off these notifications, go to Project Web Access, click Personal
Settings on the left menu, and then click Manage My Alerts and Reminders.

From this page, you can clear the check box for those notifications you no
longer want to receive.

Microsoft Office Project Server
 
A

Andrew Lavinsky

You can only have one Issues list type in a workspace. That being said,
you can create a list from another list template, and that should work -
as long as you don't call it "Issues."

The only trick will be to add the right custom fields to the template. That
might be a bit tedious the first time, but with content types and list templates,
that should be easy for other sites.

What to you mean link to other items such as documents? Do you mean attach
documents? Or link to tasks in MS Project?

- Andrew Lavinsky
Blog: http://blogs.catapultsystems.com/epm
 
T

Tim Mccoy

Thank you for the quick reply Andrew.

When I refer to "linking" I am not referring to attaching documents. I am
referring to the "Link" button that appears when you edit the list item. It
allows you to link Project Tasks, Project Documents, etc. to the list item as
a reference.

Thank you!

Tim
 