MSPS 2007 (SP1) - Task is 100% but Still Has Remaining Work Hours

T

Tim Mccoy

I know this sounds wrong but... Any idea why I have a task that is marked as
100% complete and still has hours in the remaining work field? How did I
cause this to happen?

Here are the fields and their values:
Work: 1010 hours
Baseline Work: 181 hours
Duration: 178 days
Actual Work: 181 hours
% Complete: 100%
% Work Complete: 100%
Remaining Work: 829 hours
Resource Name: Blank

I tried recreating this in a new/blank plan and cannot recreate the issue.

We use this "generic" task to track hours expended on the project before it
kicks off.

Thank you!
 