MSPS 2007 - Tracking Work Progress View in PWA

T

Tim Mccoy

I am using MSPS 2007.

Does anyone have any insight (or documentation) into a view in PWA which
shows progress (or lack of) based on work performed in both Project Center
and at the Project levels?

I am trying to create something similiar to what you get in the thick client
using the 'Check Progress' view and applying the 'Late Tasks' filter.

Thank you!
 
T

Tim Mccoy

Thank you for the suggestion, the tracking view is not close to what I am
trying to do.

I am trying to identify late tasks based on how much work should have been
completed as of the current date, similiar to the tracking or 'Check
Progress' view in the thick client. Example: If I am 25% complete on a 4 day
and today is the 3rd of 4 days, I am late on the task. This is one example,
I am sure there are other methods that would be appropriate.

Any suggestions?

Thank you.
 