Multi-national calendars

S

Steve Scott

I can't remember if this is an issue, but am I right in saying that if I have
3 x seperate countries operating different bank holidays, different working
hours per day in their project templates then I just set the templates and
calendars up accordingly and everything should work ok on one server instance
being used by the 3 different sets of users?

Is there however a limitation in timesheet hours per day that can only have
one setting across the whole enterprise which might differ from country to
country? Also, I can't remember, can I have 3 x different currency symbols
operating across the plans and if so what happens to costs in PWA views?

thanks in advance.
 
B

Ben Howard

Hi Steve, the calendar peices should work okay, but you are right in terms of
timesheets.

Project Server allows you to save projects in different currencies, but it
makes no differentation between the currencies in the PWA views (and
therefore in the summation of the values). It might be worth having a
separate project enterprise field called currency which would then at least
allow you to group by currency if you needed to roll up the values.
 