S
Shalem
Hello everyone, and thanks in advance for trying to help me achieving
the following, in Server 2007 SP1 environment:
Let us say we have PROJECT1 and PROJECT2, managed by PM1 and PM2,
accordingly.
Only one RESOURCE is working, 70% of his time to PROJECT1 and 30% to
PROJECT2.
Can I make this senario work:
PM1 opens PROJECT1, building team from enterprise (RESOURCE only will
work on this project).
PM1 open resource sheet, and changing MAX UNITS for RESOURCE to 70%
understanding that theses changes will reset when the plan is reopen,
because this is an enterprise resource.
PM1 then assigning RESOURCE to all of the tasks, and obviously the
resource is allocated to more than 70%, because some taksk occure at
the same time (in PROJECT1 itself), so PM1 wants to do "resource
leveling" so that the tool will automaticly delay or split tasks in
PROJECT1 so RESOURCE will not work more than 70% in PROJECT1,
regardless of the situation in PROJECT2. PM1 also wants that in the
resource sheet view, RESOURCE will appear in red if and only if
RESOURCE is allocated above 70% in PROJECT1.
PM2 wants excactly the same, and if they both level RESOURCE to 70%
and 30%, so in total the resource will not be overallocated.
Can I make this happen? how? will deselecting the "Load summery
resource assignment" checkbox when openning the project do the job?
Thanks again
Shalem.
the following, in Server 2007 SP1 environment:
Let us say we have PROJECT1 and PROJECT2, managed by PM1 and PM2,
accordingly.
Only one RESOURCE is working, 70% of his time to PROJECT1 and 30% to
PROJECT2.
Can I make this senario work:
PM1 opens PROJECT1, building team from enterprise (RESOURCE only will
work on this project).
PM1 open resource sheet, and changing MAX UNITS for RESOURCE to 70%
understanding that theses changes will reset when the plan is reopen,
because this is an enterprise resource.
PM1 then assigning RESOURCE to all of the tasks, and obviously the
resource is allocated to more than 70%, because some taksk occure at
the same time (in PROJECT1 itself), so PM1 wants to do "resource
leveling" so that the tool will automaticly delay or split tasks in
PROJECT1 so RESOURCE will not work more than 70% in PROJECT1,
regardless of the situation in PROJECT2. PM1 also wants that in the
resource sheet view, RESOURCE will appear in red if and only if
RESOURCE is allocated above 70% in PROJECT1.
PM2 wants excactly the same, and if they both level RESOURCE to 70%
and 30%, so in total the resource will not be overallocated.
Can I make this happen? how? will deselecting the "Load summery
resource assignment" checkbox when openning the project do the job?
Thanks again
Shalem.