Multi-Project Resource Leveling with Project Server 2003

J

Jerry Mapp

Do you open multiple enterprise projects in MS
Professional 2003 and then resource leveling, saving all
projects back to the project server? Or do you have to
dump all the enterprise resources into a separate
project, then open all enterprise projects you want to
level across, level them, and then save them back to the
server?
 
D

Dale Howard [MVP]

Jerry --

In order to level an overallocated resource in Project Server 2003, you must
open all of the projects to which that resource is assigned before leveling.
Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top