S
Serge Locas
We are using Project 2003 with Project Server 2003 to
manage all work done in the IT organization.
A resource X may be assigned part time (ex. 40%, 2d per
week) on project A and also part-time on project B (ex.
60%).
Project Manager A must level resource X usage such that
he will not used more than 40% of the available time of
resource X on his project (Project A). The same way,
Project Manager B must level resource X usage such that
he will not used more than 60% of the available time of
resource X on his project (Project B).
How do we configure Project Professional 2003 and/or
Project Server 2003 on both project, to be able to use
the resource leveling function to spread the resource's
usage taking into consideration the Max Unit of that
resource assigned to the specific project???
manage all work done in the IT organization.
A resource X may be assigned part time (ex. 40%, 2d per
week) on project A and also part-time on project B (ex.
60%).
Project Manager A must level resource X usage such that
he will not used more than 40% of the available time of
resource X on his project (Project A). The same way,
Project Manager B must level resource X usage such that
he will not used more than 60% of the available time of
resource X on his project (Project B).
How do we configure Project Professional 2003 and/or
Project Server 2003 on both project, to be able to use
the resource leveling function to spread the resource's
usage taking into consideration the Max Unit of that
resource assigned to the specific project???