Multi Value Resource Enterprise Outline Codes - Reporting on from Database

T

TroyS

has anyone run across reporting on the multi-value Resource Enterprise
Outline Codes?
For example, i have Ent Ouline Code 23 for Certifications which is a
multi-value select list

In project pro, I can insert Ent Outline Code 23 either as a single value
column or i see a separate MV-Ent Outline Code 23 listed and can be inserted
separately.

I'm trying to pull the multiple values checked for each resource into a
custome report, but i'm not seeing how those multiple values are being
stored in the database.

any suggestions? thx.
 
D

Dale Howard [MVP]

TroyS --

You should post your question in the microsoft.public.project.developer
newsgroup, as the solution to your problem will require custom development
of some type. Hope this helps.
 