Multi Value codes are restricted to Enterprise Resource Outline Codes (20-29)
The nearest you can get in Enterprise Project Outline Codes is to use more
than one field - but to share the values ... the main benefit of this is that
you maintain the list in a single location and propogate to as many other
codes as required maintaining data integrity
You can use the multiple fields in Project Centre views using multi field
filters with (AND) conditions
This is a work around only and clearly does not offer the flexibility of
Multi Values ... but its a start
Hope it helps
--
Regards
Chris Marriott - PMP MCSE MCDBA
UK - EPM Consultant & Trainer