M
Manoj Balan
In my project, the development activities are based on a 5 day week
manner and the project implementation is based on a 6 day week. So
I've created two different calenders (5 day week as project calender
and 6 day week for implenetation tasks) for my project. And I could
manage the scheduling. But when I checked the total duration(Summary
task), it is calculated based on the Project calendar, ie , the 5 day
wek calendar. So it shows less than the actual duration. Is there any
way to specify the formula for the summary task for the "Duration"
field.
Thanks in advance
MB
manner and the project implementation is based on a 6 day week. So
I've created two different calenders (5 day week as project calender
and 6 day week for implenetation tasks) for my project. And I could
manage the scheduling. But when I checked the total duration(Summary
task), it is calculated based on the Project calendar, ie , the 5 day
wek calendar. So it shows less than the actual duration. Is there any
way to specify the formula for the summary task for the "Duration"
field.
Thanks in advance
MB