multiple calendar in single project

M

Manoj Balan

In my project, the development activities are based on a 5 day week
manner and the project implementation is based on a 6 day week. So
I've created two different calenders (5 day week as project calender
and 6 day week for implenetation tasks) for my project. And I could
manage the scheduling. But when I checked the total duration(Summary
task), it is calculated based on the Project calendar, ie , the 5 day
wek calendar. So it shows less than the actual duration. Is there any
way to specify the formula for the summary task for the "Duration"
field.

Thanks in advance
MB
 
R

Rod Gill

I would follow the practice of one project for development and one for
implementation. Implementation may well suit a different PM and certainly
has different skills involved (though still some development for bug fixing
etc).

Alternatively assign the 6 day calendar to all tasks that need it under the
advanced tab of the Task Information dialog.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top