Multiple constraint dates on 1 activity

P

PeterJGreen

I have an activity that can only occur on a 2 weekly cycle, although its
predecessor can happen at any time. For example, currently the predecessor
completes on 12/05 and the activity in question occurs on the 14th, however
if the predecessor slips by 3 days, the next day the activity (a fortnightly
board meeting) can occur is the 28th. Is there anyway of automating this so
the meeting will only occur when required?
 
G

Gérard Ducouret

Hello Peter,

Create a special Calendar "Fortnightly Meeting" and set the working days as
need. then assign this calendar to the task : Task Information / Advanced /
Calendar

Gérard Ducouret
 
A

AndyB

Hi Peter,

As Gerard points out but alternately you can insert a recurring task
[Insert/Recurring Task] for all the fortnightly board meetings. This will
allow you to link either to them all or to any individual task incorporated
in the recurring task list. This may prove a little easier.

AndyB.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top