P
PeterJGreen
I have an activity that can only occur on a 2 weekly cycle, although its
predecessor can happen at any time. For example, currently the predecessor
completes on 12/05 and the activity in question occurs on the 14th, however
if the predecessor slips by 3 days, the next day the activity (a fortnightly
board meeting) can occur is the 28th. Is there anyway of automating this so
the meeting will only occur when required?
predecessor can happen at any time. For example, currently the predecessor
completes on 12/05 and the activity in question occurs on the 14th, however
if the predecessor slips by 3 days, the next day the activity (a fortnightly
board meeting) can occur is the 28th. Is there anyway of automating this so
the meeting will only occur when required?