S
scottsoo9
Here is the problem
I know when I am going to start the task and the last day the task ca
be finished by. My question is I have three other dates that need to b
added in between the start and finish date. These three dates check o
the task and make sure everything is going alright. Should I just ad
in three more start dates as start date1, start date2, and start date
or is there a better way to go about doing this.
Also for each task, I have alot of information where I had to add mor
text columns and it is getting pretty messy to look at. Is there a wa
to be able to minimize all the added columns without having to hide eac
one. (ex.Somehow have minimize button where those colomns will fold u
on demand.
Any responses are appreciated. Thanks, Scot
I know when I am going to start the task and the last day the task ca
be finished by. My question is I have three other dates that need to b
added in between the start and finish date. These three dates check o
the task and make sure everything is going alright. Should I just ad
in three more start dates as start date1, start date2, and start date
or is there a better way to go about doing this.
Also for each task, I have alot of information where I had to add mor
text columns and it is getting pretty messy to look at. Is there a wa
to be able to minimize all the added columns without having to hide eac
one. (ex.Somehow have minimize button where those colomns will fold u
on demand.
Any responses are appreciated. Thanks, Scot